The key stages of the Jourdain program
2018 to 2021
Preliminary studies
Mis 2021
Launch of the treatment unit design
February 2022
Start of work on the treatment unit
Mid 2023
Completion of the treatment unit
For 12 months
Operation of the treatment unit with discharge into the ocean to ensure processing performance
Mid 2024
Construction of the transfer pipeline and the vegetated transition zone
2024 to 2026
Evaluation of operational impacts (environmental, health, social) and conduct of research and innovation projects associated with the different themes of the program.
2027
Assessment and evaluation of the entire Jordan programme
Beyond 2027
Contribution of results to possible regulatory developments.
Extension of the system’s capacity to 600 m3/h for a long-term solution (subject to the necessary authorizations).
Possible deployment of similar solutions in other territories in France.